Network extension for new irrigation scheme at Waihao Downs, 60km south of Timaru.

A new irrigations scheme is in the process of being developed at Waihao Downs approx. 60km south of Timaru. In order to supply electricity an extension of the network is required.

Two new circuits will be built: one express circuit from the Bells Ponds zone substation to the Waihao Downs pumping station; and one distribution circuit to supply the Waihuna Feeder.

Despite the recent cold temperatures the project with a planned duration of eight weeks has started. 120 new power poles have been installed and will be wired with Jaguar conductor over a length of 8kms. 52kms of Jaguar will be used to wire the 11kV double circuit.

Waihao Downs Irrigation

Waihao Downs Irrigation

 

Share this post

Submit to DeliciousSubmit to DiggSubmit to FacebookSubmit to Google PlusSubmit to StumbleuponSubmit to TechnoratiSubmit to TwitterSubmit to LinkedIn

ALPINENERGY Logo Web

NETcon is the main contractor to Alpine Energy.

Infratec Logo Web

Infratec is a division of NETcon, specialised in end-to-end renewable energy.

Energy Made Clean is Infatec's strategic alliance partner based in Perth.

Back to top