Substation

Timaru, Fonterra and Rangitata substation installations

Timaru Substation:

Upgrade of 11kV feeder circuits onto new Transpower RPS switchboard supplying 30,000 customers in the South Canterbury region.
22 circuits installed, tested and commissioned totaling 10 km of underground cabling.
Continuity of supply to every customer at all times throughout duration of the project.
Delivered on time, on budget and exceeding customer expectations following over 12,000 man hours on site.
H&S delivered as per Transpower’s exacting standards with no lost time injuries or major incidents.

Fonterra Clandeboye Substation

Install and commission 2 x 25MVA 33/11kV transformers and protection.
Install and commission 33kV CBs.
Commission 11 x VCB 11kV switchboard and protection.

Rangitata Substation Alpine Energy Ltd

Install and commission 5 x VCB 11kV switchboard and protection.
Install and commission 2 x 3MVA 33/11kV transformers.
Install and commission 3 x 200Amp 11kV voltage regulator bank.

Share this post

Submit to DeliciousSubmit to DiggSubmit to FacebookSubmit to Google PlusSubmit to StumbleuponSubmit to TechnoratiSubmit to TwitterSubmit to LinkedIn

ALPINENERGY Logo Web

NETcon is the main contractor to Alpine Energy.

Infratec Logo Web

Infratec is a division of NETcon, specialised in end-to-end renewable energy.

Energy Made Clean is Infatec's strategic alliance partner based in Perth.

Back to top